Figure 7 – 12 usesS-curvestodisplayEVdataforaprojectthatisperformingoverbudgetand
behindschedule.


125 .Answer:D.


PMBOK® Guide, pages 260 – 265 , Section 7. 4. 2. 2 ; and Figure 7 – 12


Earned Value Management


...


Variances from the approved baseline will also be


Monitored:


...


Costvariance.Costvariance(CV)istheamountofbudgetdeficitorsurplusatagivenpointintime,
expressedas the differencebetween earnedvalue and theactual cost.Itis ameasure of cost
performanceonaproject.Itisequaltotheearnedvalue(EV)minustheactualcost(AC).Thecost
varianceattheendoftheprojectwillbethedifferencebetweenthebudgetatcompletion(BAC)and
the actual amount spent. TheCV is particularlycritical becauseitindicates the relationshipof
physicalperformancetothecostsspent.NegativeCVisoftendifficultfortheprojecttorecover,
EquationCV=EV–AC


TheSVandCVvaluescanbeconvened toefficiencyindicators toreflectthecostandschedule
performanceofanyprojectforcomparisonagainstallotherprojectsorwithinaportfolioofprojects.
Thevariancesareusefulfordeterminingprojectstatus.


...


Costperformanceindex.Thecostperformanceindex(CPI) isameasureofthecostefficiencyof
budgetedresources,expressedasaratioofearnedvaluetoactualcost.Itisconsideredthemost
criticalEVMmetricandmeasuresthecostefficiencyfortheworkcompleted.ACPIvalueoflessthan



  1. 0 indicatesacost overrunforworkcompleted.A CPIvalue greaterthan 1. 0 indicates acost
    underrunofperformancetodate.TheCPIisequaltotheratiooftheEVtotheAC.Theindicesare
    usefulfordeterminingprojectstatusandprovidingabasisforestimatingprojectcostandschedule
    outcome.Equation:CPI=EV/AC


Thethreeparametersofplannedvalue,earnedvalue,andactualcostcanbemonitoredand reported
onbothaperiod-by-periodbasis(typicallyweeklyormonthly)andonacumulativebasis. Figure 7 –
12 usesS-curvestodisplayEVdataforaprojectthatisperformingoverbudgetandbehindschedule.


126 .Answer:D.


PMBOK® Guide, Pages 260 – 265 , Section 7. 4. 2. 2 ; and Figure 7 – 12


Earned Value Management


TheSVandCVvaluescanbeconvertedtoefficiencyindicatorstoreflectthecostandschedule
performanceofanyprojectforcomparisonagainstallotherprojectsorwithinaportfolioofprojects.
Thevariancesareusefulfordeterminingprojectstatus.


Schedule performance index. The schedule performance index (SPI) is a measure of schedule
efficiencyexpressedastheratioofearnedvaluetoplannedvalue.Itmeasureshowefficientlythe