projectteamisusingitstime.Itissometimesusedinconjunctionwiththecostperformanceindex
(CPI)toforecastthefinalprojectcompletionestimates.


AnSPIvaluelessthan 1. 0 indicateslessworkwascompletedthanwasplanned.AnSPIgreaterthan



  1. 0 indicatesthatmoreworkwascompletedthanwasplanned.BecausetheSPImeasuresallproject
    work,theperformanceonthecriticalpathalsoneedstobeanalyzedtodeterminewhetherthe
    projectwillfinishaheadoforbehinditsplannedfinishdate.TheSPIisequaltotheratiooftheEVto
    thePV.Equation:SPI=EV/PV


...


Thethreeparametersofplannedvalue,earnedvalue,andactualcostcanbemonitoredand reported
onbothaperiod-by-periodbasis(typicallyweeklyormonthly)andonacumulativebasis. Figure 7 –
12 usesS-curvestodisplayEVdataforaprojectthatisperformingoverbudgetandbehindschedule.