  1. Answer: C.


PMBOK® Guide, pages 466 - 467 , Section 12.1; and Figure 12 - 2


The Plan Procurement Management process has the followinginputs:


 Projectcharter
 Businessdocuments
o Businesscase
o Benefits management plan
 Project managementplan
o Scope managementplan
o Quality management plan
o Resource managementplan
o Scopebaseline
 Projectdocuments
o Milestone list
o Project teamassignments
o Requirementsdocumentation
o Requirements traceabilitymatrix
o Resourcerequirements
o Riskregister
o Stakeholderregister
 Enterprise environmentalfactors
 Organizational processassets


  1. Answer: A.


PMBOK® Guide, page 477 , Section12.1.3.3


ProcurementDocumentation


Procurementdocumentationprovidesawrittenrecordusedinreachingthelegalagreement,and
may include older documents predating the current project. Procurement documentation can
include:


BidDocuments.DescribedinSection 12. 1. 3. 3 ,procurementdocumentsincludetheRFI,RFP,RFQ,or
otherdocumentssenttosellerssotheycandevelopabidresponse.


12.2.1.4 Seller Proposals


Seller proposals, prepared in response to a procurement document package, form the basic
informationthatwillbeusedbyanevaluationbodytoselectoneormoresuccessfulbidders (sellers).
Ifthesellerisgoingtosubmitapriceproposal,goodpracticeistorequirethatitbe separatefrom
thetechnicalproposalaccordingtothesourceselectioncriteriaandselectstheseller thatcanbest
satisfythebuyingorganization’srequirements.