248.Answer:A.
PMBOK® Guide, page 199 , Section 6.4.1.2; andGlossary
Resourcerequirements.Thetypesandquantitiesofresourcesrequiredforeachactivityinawork
package.
249.Answer:B.
PMBOK® Guide, page 19 , Section 1.2.4.1; andGlossary
Adaptive life cycle. A project life cycle that is iterative orincremental.
250.Answer:C.
PMBOK® Guide, page 200 , Section 6.4.2.2; andGlossary
Analogousestimating.Atechniqueforestimatingthedurationorcostofanactivityoraprojectusing
historicaldatafromasimilaractivityorproject.
251.Answer:D.
PMBOK®Guide,Glossary
Assumption.Afactorintheplanningprocessthatisconsideredtobetrue,real,orcertain;without
proofordemonstration.
252.Answer:A.
PMBOK® Guide, page 204 , Section 6.4.3.2; andGlossary
Basic of estimates. Supporting documentation outlining the details used in establishing project
estimatessuchasassumption,constraints,levelofdetail,range,andconfidencelevels.
253.Answer:B.
PMBOK® Guide, page 30 , Section 1.2.6.1; andGlossary
Businesscase.Adocumentedeconomicfeasibilitystudyusedtoestablishvalidityofthebenefitsofa
selectedcomponentlackingsufficientdefinitionandthatisusedasabasisfortheauthorizationof
furtherprojectmanagementactivities.
254.Answer:C.
PMBOK®Guide,Glossary
Checklistanalysis.Atechniqueforsystematicallyreviewingmaterialsusingalistforaccuracyand
completeness.