H. IU 3: 5000 TPD, Integrated Unit at Karnataka
S. N. Buildings (M3)RCC R/f Steel(MT) R/f Factor(Kg/m3)
Clinkerisation Section
1 Lime Stone Stock pile 2,367 129 54
2 Coal Stockpile 1,686 92 55
3 Corrective/Additive stockpile 2,117 106 50
4 Blending Silo 1,806 419 232
5 Unburnt Clinker Hopper/Silo 468 64 137
6 Clinker Silo 6,690 950 142
7 Preheater Tower + compressor 6,100 1,397 229
8 Kiln Piers & TA Duct 1,808 73 40
9 Cooler + Cooler ESP + DPC 2,231 236 106
10 Raw Material Hopper 701 87 124
11 Raw Mill Building 2,652 297 112
12 Raw Mil Bag House 1,336 143 107
13 Wagon Tippler 288
14 Truck Tippler 3,007
15 Coal Mill + Coal Mill Hopper 1,694 173 102
16 LS Crusher 3,671 307 84
17 Belt Conveyors + Transfer Towers 4,140 383 93
Total - Clinkerization 42,474 5,144 121
Grinding Section
1 Fly Ash Silo 761 103 135
2 Cement Silo 2,097 467 223
3 Cement Mill Building & Bag House 4,161 557 134
4 Cement Mill Hopper 576 67 116
5 Packing Plant + Empty Bag Godown + Truck Loading 3,080 333 108
6 Bulk Loading Silo 1,030 271 263
7 Fly Ash Dump Hopper 703 100 142
8 Wagon Loading platform & Shed 1,037 239 230
9 Packing Plant MCC Room 715 49 69
Total - Grinding 14,160 2,186 154
Common Facilities