Comparison for 4/ 5/6 Stage Preheater (Estimation at 9500 TPD Capacity)
PH Stage Reduction
Remarks
Data Unit 4 stage 5 Stage 6 StageSteel and
fabrication
weight of
cyclone
Lacs Rs -360 -180 0AS calculated
90 Tonnes of 1
cyclone of each
string
Steel &
fabrication cost
considered Rs
100000/tDip tube cost Lacs Rs -196.8 -98.4 0
8.2 T dip tube
weight /Rs 600
kg cost /tubeRefractory
- Double
insulation
weight
Lacs Rs -476 -238 0Refractory
weight
considered 680
for 2 cyclone
and both strings
Refractory cost
considered
Rs 35000 /t
including layingDown comer
duct Lacs Rs -25.6 -12.8^0
Steel weight
for 16 meter for
each stageKiln feed BE
cost Lacs Rs -48 -24^0
BE cost
considered
1.5 lacs/meter.
Approx. height
by 16 meter in
one stage
Total Capital
Cost In Cement
Plant Savings