technical NOTES

(Project Pridr) #1

Comparison for 4/ 5/6 Stage Preheater (Estimation at 9500 TPD Capacity) 
PH Stage Reduction
Remarks
Data Unit 4 stage 5 Stage 6 Stage
Differential PH
Fan Sp. Power
consumption


KW / of T
clinker -0.110 -0.008 0.000




Differential
Bucket elevator
Sp. Power
consumption


KW / of T
clinker

-0.195 -0.100 0.000 


Total Saving
on Power
(including
generation)


KW / of T
clinker

41.4 34.7 31.3 


Saving
for power
generation
(Net ) (+)


Rs lacs / year 8825 7389 6682 

Cost on
additional
Sp. Heat
consumption
(-)


Lacs Rs/ year 1411 627 0 

Total Opex Lacs Rs/ year 7415 6762 6682 
Differential
Opex
Lacs Rs/ year 733 80 0 


Capex


Differential PH
civil concrete
cost


Lacs Rs -733 -367 0

Considering
11000 M3
concrete for 6
stage PH and
correspondingly
per stage factor
considered @
Rs.20000 /m3
cost