Managing Information Technology

(Frankie) #1

624 Part IV • The Information Management System


When we were negotiating with vendors for USA
Group, we weren’t really a big player in the
market and had less latitude.... As part of Sallie
Mae, we were nearly able to write our own terms
and conditions. In some cases, we were working
with vendor reps in D.C., and they were able to
make better and faster deals and were more
flexible. We told them what we wanted, and they
delivered.
—Becky Robinson, Director of Systems
Management

Three different strategies were used for installing
computer equipment in the Indianapolis facility that had
been used in Reston. (Improvements to infrastructure com-
ponents—such as backup equipment and more secure fire-
walls—were also built into the migration plans.)


1.TheAsset Swapmethod was used for equipment in
Reston ready to be retired. New equipment was pur-
chased from the hardware vendor for the Indianapolis
facility. Once the applications on the old equipment
had been moved to (installed on) the new equipment
in Indianapolis, the old equipment in Reston was
traded in to the vendor.
2.ThePush/Pullstrategy was used for select equip-
ment in Reston that was not ready to be retired and
difficult to replace: the old equipment was taken out,
moved, and reinstalled in Indianapolis.
3.TheSwingmethod was used for equipment that
existed in multiples. New equipment was purchased
for Indianapolis for the earliest moves. After the ini-
tial applications were successfully installed on the
new equipment, the relevant piece of equipment was
removed from Reston and shipped to Indianapolis
for the next move, and so on.

The strategy choice for each move element was
based on allowable downtime for the application(s)
involved, vendor prices for replacement equipment and
trade-ins, and physical move costs. The overall objective
was to decrease integration risks by minimizing the hard-
ware assets that would be physically moved from Reston
to Indianapolis. For example, a Reston data warehouse
was stored on a Sun E10K server. Since this was a very
expensive piece of equipment, an asset swap strategy
would have been very costly. However, it was learned that
the business could tolerate up to a week of downtime out-
side of the peak processing season, so a push/pull strategy
was used instead. The vendor tore down the machine in
Reston, trucked it to Indiana, and rebuilt it at the
Indianapolis facility.


Lack of backup was the biggest risk. We determined
the maximum downtime that the operation could
handle without losing customers, and we established
backup and system redundancies as needed.
—John Bennett, Project Manager for Data Center
Relocation

In contrast, the company couldn’t afford much
downtime for the mainframe on which the Class loan-
servicing system was run: the service centers needed to be
able to communicate with customers. The push/pull
method required too much downtime, so the asset swap
method was used. For DASD storage, a new vendor was
selected in order to provide newer technology that would
better handle the company’s increased storage needs, as
well as reduce the maintenance risks associated with older
technologies.
Redundancies were built in, wherever possible, to
minimize the business impact of the “go live” dates of crit-
ical applications. For example, beginning in March 2001,
three T1 lines were leased from AT&T in order to have a
fast electronic backup for the major moves.

We spent a lot of money, almost a million dollars in
two months, to create a pretty significant pipe between
the two centers, in order to have a very fast link, so that
you could essentially run the business out of either
center if your migration had a problem. Fortunately,
most of our migrations went well, and they did not
have any problems, but that was a great big insurance.
—Hamed Omar, Senior Vice President, Technology
Group

Prior to any move, the sending technology owners
worked with the target (receiving) technology owners to
transfer the knowledge needed by the Indianapolis opera-
tions staff to handle the changes in applications, hardware,
and large increases in transaction volume.

Early in the process, we asked teams to start plan-
ning and scheduling tasks related to training. The
approach was tell them, show them, watch them.
—Allan Horn, Vice President, Technology
Operations

The Major Data Center Moves
The DCR team began moving applications in February
2001, as they were ready (see Exhibit 10). From the
director level down, the IT staffs at Reston and Indianapolis
Free download pdf