Increasing OEE
Breakdown OEE
▪ Review the formula in detail
▪ Work through an OEE Calculation on flip chart
▪ Availability 67% x Performance rate 86% x Quality Rate 92% = 53%
▪ If we keep performance and quality at the same and drive availability
to best in class levels of 90% what is the result? 71% therefore in
order to drive OEE, maintenance alone will not be successful, it
requires cross functional support and a focus on process control.
▪ Discuss the losses and discuss which losses typically relate to what
function
Influence of OEE On Earning Power
Figure 9 : The earning power of a plant under some assumptions
Figure 10 : OEE increase of 10% gives $9.3M in increased profit