APPENDICES


A. Answer Keys


1. Pre-Assessment


# Answer


  1. B

  2. C

  3. D

  4. A systems engineering process for establishing and maintaining
    consistency of a product's performance, functional, and physical
    attributes with its requirements, design, and operational
    information throughout its life

  5. B

  6. C

  7. D

  8. C

  9. C

  10. C

  11. D

  12. B

  13. A

  14. A

  15. B


2. Post-Assessment (Jeopardy Style)


# Answer


  1. An organization’s dream

  2. RASI Diagram

  3. An organization’s purpose

  4. Specific, Measurable, Attainable, Relevant, and Time-Bound


# Answer


  1. Anyone in the organization’s internal and external environment that
    are affected by the organization’s decision and actions

  2. Overall Equipment Effectiveness

  3. Availability x Performance rate x Quality Rate

  4. Total Productive Maintenance

  5. Define, Measure, Analyze, Improve, Control

  6. Any of these: 5 - Why, Sequence of Events, Event and Causal Factor
    (ECF) Analysis, Fault Tree Analysis, Logic Tree Analysis, Cause and
    Effect, FMEA, FMECA

  7. 6

  8. Random and age-related

  9. Failure Reporting and Corrective Action System

  10. A quantitative state of what the asset or system is required to
    perform

  11. The effect by which a failure is observed on the failed item

  12. An international standard that specifies requirements for an asset
    management system within the context of the organization

  13. 80

  14. Forming, Storming, Norming, Performing

  15. 8

  16. A common set of values, beliefs, attitudes, perceptions, and
    accepted behaviors shared by individuals within an organization.

  17. Weeks

  18. 2 weeks

  19. Job Plan Library

  20. Subjective tasks

  21. Asset Criticality & Work Priority