paimio sanatorium

(Jacob Rumans) #1
Chapter 3 | The Building of Paimio Sanatorium

ceiling and the top part of the kitchen staircase had proved more complicated to


execute than anticipated. Casting the roof had been omitted following the instruction


of the supervisors and the water storage tank had not been built owing to its sensitive


nature. Furthermore, the developer had delivered to the site on behalf of the contrac-


tor the special bricks for the horizontal section of the central heating piping. It was


estimated that the cost savings made by omitting certain work and the costs incurred


by additional work could be offset against each other.


The foundation work carried out by the developer had revealed that the bedrock


on the site required drilling which had delayed the beginning of the framework.


Although the completion of the building frame work was postponed for the above


reason until a less opportune season, the contract was completed within the set time.


The contractor emphasised the fact that receiving working drawings and structural


calculations on time had sped up the work. According to the contractor, the super-


visors had also agreed on all actions in a timely manner. The developer signed off the


work, the casting of the roof slab and the water storage tank supported by the central


heating chimney excepted.^721 Ahti built the water storage tank, which was part of


the building frame contract, in summer 1931.^722 The final inspection report does not


mention any test loads as stipulated in the new concrete building standards or that


any test cubes of the reinforced concrete structure were sent for examination at the


material testing laboratory.^723


The contract also included the purchasing of all building materials and tools and


equipment. The structures were cast in situ in timber formworks, except for the col-


umns in the lobby, which were cast in three-millimeter sheet metal formworks.^724 The


contractor purchased timber from the Building Board to build the formworks^725 and


had access to sand and water on the sanatorium plot without charge. The aggregate


for the reinforced concrete was pit-run gravel from the near vicinity of the sanato-


rium. The developer was, however, responsible for purchasing coke cinder and any


other fillers. The lift towers built by the contractor remained in the possession of the


developer after project completion. The Building Board purchased timber form Con-


tractor Arvi Ahti as well as two motors, a hoist and other machinery. He also rented


two stone mills, two hoists, a pump and a steam generator, among other things.^726


At a minimum, the following machinery was in use at the building site: a motorised


concrete mixer; one new and one old electric motor; circular rip saw and its motor;


annular water pump; weighing machine; pushcarts; hand pump, kitchen cooker; two


telephones and various mechanical devices such as iron pushcarts which were used


721 Minutes of the final inspection, December 5, 1930. PSA.
722 Building Committee July 4, 1931, Section 1. PSA.
723 Minutes of the final inspection, December 5, 1930. PSA.
724 Aalto [1930]a, p. 8. AAM.
725 On commencing the frame construction, the Building Committee sold Arvi Ahti timber from forest clearance as con-
crete structure props at a minimum price of FIM 2.75 a piece. Building Committee June 27, 1930, Section 2. PSA.
726 Building Board December 15, 1930, Section 3. PSA; Building Committee August 21, 1931, Section 3. PSA.
Free download pdf