paimio sanatorium

(Jacob Rumans) #1

since 1930. The water pipe system, including the well, the pumps and water storage tank,


had already been completed and the pipeline leading from the pump house to the main


building laid before the main construction project began. The work had been carried out by


Vesijohtoliike Onninen^940 , which in other words was to continue work on the site.


The company Radiator drew up water, sewer and heating equipment specifications


between August and October 1931. A separate ventilation design was not provided. The


water, hot water and drain pipes for the sanatorium main building, the Junior Physicians’


and the Administrative Director’s building, the workers’ apartment building as well as the


garage formed a joint system, while the Medical Director’s house had a separate system.


Similarly, all other buildings apart from the Medical Director’s house were heated by the


heating plant located on hospital grounds, while the Medical Director’s house had its own


heating station. The work was to be carried out in compliance with regulations adopted by


the City of Turku for similar projects, unless otherwise agreed.^941


In terms of the installation work, the work specifications required that the water and


drain pipes be placed within accessible shafts, or covered by a wall in a few places, or freely


in front of a wall. As a rule, the specifications stated that the design and construction of


the pipe system should aim at minimising noise.^942 Rain water was directed from the roof


via a downpipe to the basement, where it flowed into the main sewer via water traps. Cold


water pipes ran within the building. The building was equipped with fire hydrants. Film


rooms were equipped with three automatic heat-sensitive sprinklers.^943


The general heating system selected for the sanatorium was a central heating pump


system.^944 The work specification drew special attention to reducing the noise of the


two circulation pumps to a minimum. Steam heating was used as a secondary system


for areas where heating was necessary even in the summer, when the main system was


out of service. Steam was also required for water boilers and various machines and


equipment, such as the mangle, soup kettles, washing machines, disinfection equipment


and sterilisation stations. In August 1931, the Building Board decided to order furnace


940 Building Committee September 15, 1930, Section 1. PSA.
941 Specification of the water, sewage and heating systems, pp. 2 and 6. Specifications, cost calculations and
contracts. PSA.
942 All joints in any piping placed within risers had to be accessible through service hatches. In rooms, mainly in
buildings A and B, where all piping ran hidden and the walls had hard surfaces, each visible pipe section had to
be chromed. Ibidem, pp. 2–3.
943 Ibidem, p. 4.
944 The central boiler station was fitted with two 2,000 litre boilers that could heat water to 70 degrees centigrade
in one hour. Hotwater pipes were made of drawn copper pipe. The piping was equipped with supply and return
pipes and electrical centrifugal pumps. Water circulation was optimised so that only one litre of cooled-down
water at most needed to be run to obtain hot water, regardless of the outlet. To achieve even circulation, each
riser and group was equipped with an electrical valve and each pipeline, including the main and supply and return
pipes, were installed with a stop valve. The hot water pipes were insulated. The expansion U-bends were placed
at 12 metre intervals at a maximum. Ibidem, pp. 5–6.
Free download pdf