ProjectScope Statement


Theprojectscopestatementisthedescriptionoftheprojectscope,majordeliverables,assumptions,
andconstraints.Theprojectscopestatementdocumentstheentire scope,including projectand
product scope. It describes the project's deliverables in detail. It also provides a common
understanding of the project scope among project stakeholders. It may contain explicit scope
exclusions that canassistin managingstakeholder expectations. Itenables the projectteam to
performmoredetailedplanning,guidestheprojectteam'sworkduringexecution,andprovidesthe
baseline forevaluatingwhetherrequestsforchangesor additionalworkarecontained withinor
outsidetheproject'sboundaries.


Thedegreeandlevelofdetailtowhichtheprojectscopestatementdefinestheworkthatwillbe
performedandtheworkthatisexcludedcanhelpdeterminehowwelltheprojectmanagement
teamcancontroltheoverallprojectscope.Thedetailedprojectscopestatement,eitherdirectlyor by
referencetootherdocuments,includesthefollowing:


o Productscopedescription.Progressivelyelaboratesthecharacteristicsoftheproduct,service,or
resultdescribedintheprojectcharterandrequirementsdocumentation.


o Deliverables.Anyuniqueandverifiableproduct,result,orcapabilitytoperformaservicethatis
requiredto be produced to completeaprocess, phase,or project. Deliverablesalso include
ancillaryresults,suchasprojectmanagementreportsanddocumentation.Thesedeliverablesmay
bedescribedatasummaryleveloringreatdetail.


o Acceptance criteria. A set of conditions that is required to be met before deliverables are
accepted.


o Projectexclusions.Identifywhatisexcludedfromtheproject;explicitlystatingwhatisoutofscope
fortheprojecthelpsmanagestakeholders'expectationsandcanreducescopecreep.


67.Answer:A.


PMBOK® Guide, pages 156 – 157 , Section 5. 4


CreateWBS


CreateWBSistheprocessofsubdividingprojectdeliverablesandprojectworkintosmaller,more
manageablecomponents.Thekeybenefitofthisprocessisthatitprovidesaframeworkofwhathas
tobedelivered.Thisprocessisperformedonceoratpredefinedpointsintheproject.


TheWBSisahierarchicaldecompositionofthetotalscopeofworktobecarriedoutbytheproject
teamtoaccomplishtheprojectobjectivesandcreatetherequireddeliverables.TheWBSorganizes
anddefinesthetotalscopeoftheprojectandrepresentstheworkspecifiedinthecurrentapproved
projectscopestatement.


68.Answer:A.


PMBOK® Guide, page 154 , Section 5. 3. 3. 1 ; page 415 , Section 11. 2. 2. 3 ; andGlossary


Section 5. 3. 3. 1 : Project scope statement may contain explicit scope exclusions that can assist in
managing stakeholder expectations. Scope exclusions are often a result of projectconstraints.


Section 11. 2. 2. 3 : Constraints may give rise to opportunities through removing or relaxing a limiting
factor that affects the execution of a project orprocess.


Glossary: A limiting factor that affects the execution of a project, program, portfolio, or process.