C. CU 3: 6500 TPD, Clinkerisation Unit at Andhra Pradesh
D. CU 4: 6500 TPD, Clinkerisation Unit + Part Grinding Unit Extension at Rajasthan
S. N. Buildings (M3)RCC R/f Steel(MT) R/f Factor(Kg/m3)
Clinkerisation Section
1 Lime Stone Stock pile 2,194 - -
2 Blending Silo
4,195
--
3 Unburnt Clinker Hopper/Silo 460 -
4 Clinker Silo 7,455 - -
5 Preheater Tower + compressor 8,382 - -
6 Kiln Piers & TA Duct 2,451 - -
7 Cooler + Cooler ESP + DPC 3,675 - -
8 Raw Material Hopper 1,430 - -
9 Raw Mill Building
6,705
--
10 Coal Mill + Coal Mill Hopper 2,690 -
11 Belt Conveyors + Transfer Towers 475 - -
12 Switch yard and load centres 1,400 - -
Total - Clinkerization 41,512 - -
1 Clinkerisation Section 41,512 - -
2 Grinding Section - - -
3 Common Facilities - - -
4 Infrastructure - - -
Grand Total 41,512 - -
S. N. Buildings (M3)RCC R/f Steel(MT) R/f Factor(Kg/m3)
Clinkerisation Section
1 Lime Stone Stock pile 2,317 132 57
2 Coal Stockpile 146 5 37
3 Corrective/Additive stockpile 761 43 56