S. N. Buildings (M3)RCC R/f Steel(MT) R/f Factor(Kg/m3)
11 Raw Mil Bag House 2,652 455 172
12 Truck Tippler 436 34 78
13 Coal Mill + Coal Mill Hopper 2,405 338 141
14 LS Crusher 1,776 374 211
15 Coal Crusher & conveying 198 28 141
16 Belt Conveyors + Transfer Towers 2,640 223 84
17 Over Head Cable Gallery & Cable Trenches 377 38 101
18 Switch yard and load centres 850 112 132
Total - Clinkerization 44,915 7,932 177
Grinding Section
1 Fly Ash Silo 1,709 212 124
2 Cement Silo 3,726 768 206
3 Cement Mill Building & Bag House 7,298 1,323 181
4 Cement Mill Hopper 664 125 188
5 Packing Plant + Empty Bag Godown + Truck Loading 4,342 673 155
6 Clinker Crusher and screen building 277 41 148
7 Cement Mill Substation 699 115 165
Total - Grinding 18,715 3,257 174
Common Facilities
1 CCR Building 2,180 309 142
2 Workshop 436 46 106
3 H.E.M. Workshop 784 83 106
4 Weigh Bridge 129 9 70
5 Water Treatment Plant 807 77 95
6 Compressor House 206 24 117
7 General Store 259 32 124
8 Gate House 190 19 100
9 Canteen Building 121 16 132
10 Site office 131 18 137
11 Guest House 1,600 265 166
12 Other Misc. 407 18 44
Total - Common Facilities 7,250 916 126
Infrastructure