S. N. Buildings (M3)RCC TMT(MT) R/f Factor(Kg/m3)


20 Over Head Cable Gallery & Cable Trenches 2,003 117 58
21 Switch yard and load centres 1,375 162 118
Total - Clinkerization 54,542 7,376 135
Grinding Section
1 Fly Ash Silo 1,567 316 202
2 Cement Silo 3,937 784 199
3 Cement Mill Building & Bag House 7,368 849 115
4 Cement Mill Hopper 686 109 158
5 Packing Plant + Empty Bag Godown + Truck Loading 7,977 1,052 132
6 Wagon Loading platform & Shed 4,336 581 134
Total - Grinding 25,872 3,690 143
Common Facilities
1 CCR Building 2,176 281 129
2 Workshop

3,387 346 102


3 H.E.M. Workshop
4 Weigh Bridge
5 Water Treatment Plant
6 Raw Water reservoir
7 Compressor House
8 General Store
9 Gate House
10 Canteen Building
Total - Common Facilities 5,563 627 113
Infrastructure
1 Boundary Wall 1,217 78 64
2 Plant Flooring 4,259 114 27
Total - Infra 5,476 192 35
Grand Total 91,453 11,886 130
1 Clinkerisation Section 54,542 7,376 135
2 Grinding Section 25,872 3,690 143
3 Common Facilities 5,563 627 113
4 Infrastructure 5,476 192 35
Grand Total 91,453 11,886 130