(khatib.arch2) #1
http://www.alsenosy.com | http://www.professionalengineers.us

profitability.Acost-benefitanalysisforeachqualityactivitycomparesthecostofthequalitystepto
theexpectedbenefit.


131.Answer: D.


PMBOK® Guide, pages 300 – 302 , Section 8. 3. 1 ; and page 298 , Figure 8 – 10


The Control Quality process has the followinginputs:


Project managementplan


o Quality managementplan


Projectdocuments


o Lessons learnedregister
o Quality metrics
o Test and evaluation documents

Approved changerequests


Deliverables


Work performance data


Enterprise environmentalfactors


Organizational processassets


132.Answer:A.


PMBOK® Guide, page 286 , Section8.1.3.1


Quality Management Plan


Thequalitymanagementplanisacomponentoftheprojectmanagementplanthatdescribeshow
applicablepolicies,procedures,andguidelineswillbeimplementedtoachievethequalityobjectives.
Itdescribestheactivitiesandresourcesnecessaryfortheprojectmanagementteamtoachievethe
qualityobjectivesset forthe project.The qualitymanagementplan maybeformalor informal,
detailed,orbroadlyframed.Thestyleanddetailofthequalitymanagementplanaredeterminedby
therequirements oftheproject.Thequalitymanagementplanshould bereviewedearly inthe
projecttoensurethatdecisionsarebasedonaccurateinformation.Thebenefitsofthisreviewcan
includeasharperfocusontheproject'svalueproposition,reductionsincosts,andlessfrequent
scheduleoverrunsthatarecausedbyrework.


133.Answer:C.


PMBOK® Guide, page 288 , Section 8.2, Figure 8 – 7


ManageQuality


ManageQualityistheprocessoftranslatingthequalitymanagementplanintoexecutablequality
activitiesthatincorporatetheorganization'squalitypoliciesintotheproject.Thekeybenefitsofthis
processarethatitincreasestheprobabilityofmeetingthequalityobjectivesaswellasidentifying
ineffectiveprocessesandcausesofpoorquality.ManageQualityusesthedataandresultsfromthe