o Financialdatarepositoriescontaininginformationsuchaslaborhours,incurredcosts,budgets,and
anyprojectcostoverruns;
o Historical information and lessons learned knowledge repositories (e.g., project records and
documents,allprojectclosureinformationanddocumentation,informationregardingboththe
resultsofpreviousprojectselectiondecisionsandpreviousprojectperformanceinformation,and
informationfromriskmanagementactivities);
o Issue and defect management data repositories containing issue and defect status, control
information,issueanddefectresolution,andactionitemresults;
o Datarepositoriesformetricsusedtocollectandmakeavailablemeasurementdataonprocesses
and products; and Project files from previous projects (e.g., scope, cost, schedule, and
performancemeasurement baselines,projectcalendars,projectschedulenetworkdiagrams,risk
registers,riskreports,and stakeholderregisters).
25 .Answer:B.
PMBOK®Guide,page 39 ,Section 2. 2. 2
EnterpriseEnvironmental Factors
Enterprise environmentalfactors(EEFs)refertoconditions,not underthecontroloftheproject
team,thatinfluence,constrain,ordirecttheproject.Enterpriseenvironmentalfactorsareconsidered
inputstomostplanningprocesses,mayenhanceorconstrainprojectmanagement options,andmay
haveapositiveornegativeinfluenceontheoutcome.EEFsvarywidelyintypeor nature.These
factorsneedtobeconsiderediftheprojectistobeeffective.EEFsinclude,butarenot limitedto,the
factorsbelow.
ThefollowingEEFsareinternaltotheorganization:
o Organizationalculture,structure,andgovernance.Examplesincludevision,mission,values,beliefs,
culturalnorms,leadershipstyles,hierarchyandauthorityrelationships,organizationalstyles,ethics,
andcodesofconduct.
o Geographicdistributionoffacilitiesandresources.Examplesincludefactorylocations,virtualteams,
sharedsystems,andcloudcomputing.
o Infrastructure.Examplesincludeexistingfacilities,equipment,organizationaltelecommunications
channels,informationtechnologyhardware,availability,andcapacity.
o Information technology software. Examples include scheduling software tools, configuration
managementsystems,webinterfacestootheronlineautomatedsystems,andworkauthorization
systems.
o Resourceavailability.Examplesincludecontractingandpurchasingconstraints,approvedproviders
andsubcontractors,andcollaborationagreements.
o Employeecapability.Examplesincludeexistinghumanresourcesexpertise,skills,competencies,
andspecializedknowledge.
26 .Answer:C.
PMBOK®Guide,page 39 ,Section 2. 3