technical NOTES

(Project Pridr) #1

E. CU 5: 8500 TPD, Clinkerisation Unit at Odisha


S. N. Buildings (M3)RCC TMT(MT) R/f Factor(Kg/m3)
Clinkerisation Section
1 Lime Stone Stock pile 4,436 375 85
2 Coal Stockpile 4,047 344 85
3 Corrective/Additive stockpile
4 Blending Silo 3,955 716 181
5 Unburnt Clinker Hopper/Silo 798 105 132
6 Clinker Silo 5,863 1,061 181
7 Preheater Tower + compressor 13,281 3,548 267
8 Kiln Piers & TA Duct 1,360 140 103
9 Cooler + Cooler ESP + DPC 3,675 357 97
10 Raw Material Hopper 961 130 135
11 Raw Mill Building 3,435 517 151
12 Raw Mil Bag House 3,365 388 115
13 Truck Tippler 625 69 110
14 Coal Mill + Coal Mill Hopper 2,592 461 178
15 Temp LS crusher 1,059 115 109
16 LS Crusher 8,650 1,000 116
17 Coal Crusher & conveying 369 45 121
18 Corrective Crusher 233 25 107
19 Belt Conveyors + Transfer Towers 3,242 296 91
20 Over Head Cable Gallery & Cable Trenches 767 70 91
21 Switch yard and load centres 949 81 85
22 Alternate Fuel Storage Shed 2,525 155 61
23 Clinker Wagon Loading system 1,921 256 133
Total - Clinkerization 68,106 10,254 151
Common Facilities
1 CCR Building 2,334 283 121
2 Weigh Bridge 125 6 48
3 Water Treatment Plant 786 66 83
4 General Store 420 35 83
5 Gate House 300 30 100