3. 1 The Social Stakeholders of the Sanatorium Building Project 3.1.1 STATE MEDICAL BOARD HELD THE KEYS TO FUNDING In 1929 the F ...
Chapter 3 | The Building of Paimio Sanatorium the time was the City of Helsinki’s Tuberculosis Sanatorium in the district of Laa ...
3.1.2 A COLLABORATION OF MULTIPLE MUNICIPALITIES The project of building the Tuberculosis Sanatorium of Southwest Finland was la ...
Chapter 3 | The Building of Paimio Sanatorium Turku joined the project on February 15, 1930, Kaarlo Thomander^539 , master build ...
physician participated in the work of the Committee from its second meeting onwards, and civil engineer Kaarlo Albert Kilpi,^549 ...
Chapter 3 | The Building of Paimio Sanatorium Committee meetings show that most of the tenders had been addressed directly to ar ...
and was designed by architect Onni Tarjanne. At the time of its completion in 1903, it had been Finland’s first tuberculosis san ...
Fig. 3.1.3a. Detail of the competition-stage drawing No. 50-26. The drawing has been edited. AAM. [Volumes] [m^3 ] Service build ...
comprised Bernhard Heikkilä, Chairman of the Building Board and farm owner; Jussi Paatela (1906–1962) and Väinö Vähäkallio (1886 ...
Chapter 3 | The Building of Paimio Sanatorium Helsinki University of Technology.^567 The architect members of the jury were, in ...
could be and that public money should not go to waste when such a significant new piece of legislation had been passed, overrode ...
Fig. 3.1.3b. Main building ground floor plan of the competition-stage design. Drawing No. 50-25. The drawing has been edited. AA ...
The entries gaining second and third place, Valo and Ammon-Ra, were similar in their basic concepts. The buildings had L-shaped ...
Chapter 3 | The Building of Paimio Sanatorium next floor, resulting in a vault-like space at the top of the room. The northern w ...
opinion should be entirely dedicated to patient rooms and lounges. In Horelli’s opinion, the place for the nurse’s room was not ...
Fig. 3.1.3c. Main building ground floor plan in December 1929. There were still three four-person patient rooms per ward. Drawin ...
According to the second contract, the architect undertook the general management of the sanatorium construction work including t ...
of the drawings were by Aino Marsio-Aalto.^593 Most of the drawings bear the initials of Lauri Sipilä, Lars Wiklund, Erling Bjer ...
The architects used sequential numbering on certain sets of drawings, but a large proportion of the drawings were unnumbered. Am ...
SKETCHES OF THE LOBBY AREA FROM EARLY 1930 Fig. 3.1.3f. The load-bearing structure is marked with red. The main stairs have been ...
«