Dalmia DSP Success Story
52 PROjECT PRIDE Once the material reached site, the store manager used the app to provide details of unloading the equipment at ...
ExECUTION PROCEss EsTABLIsHmENT 53 executing agencies at site as soon as the same was issued as released for construction by the ...
54 PROjECT PRIDE to maintain commitment and for their smooth cash flow for this project. The Talent Acquisition team was tasked ...
ExECUTION PROCEss EsTABLIsHmENT 55 as accommodation arrangements for the selected talents at the respective locations. All our p ...
56 PROjECT PRIDE plant and machinery was selected. For construction works, we had invited offers from all the contractors in cat ...
ExECUTION PROCEss EsTABLIsHmENT 57 GRNs were made on time with existing manpower at site and handled all the commercial activity ...
58 PROjECT PRIDE attitude and spirit around Project Pride; a go-get-it attitude, transparency, ownership, responsibility, and co ...
ExECUTION PROCEss EsTABLIsHmENT 59 Since this was a fast-track project, Holtec aligned its resources to cope up with the require ...
60 PROjECT PRIDE including BBS. Advance steel was used for detailing of steel structures to provide GA, fabrication drawings, an ...
Commencement of Execution With our available resources at site, area cleaning, tree cutting, and tree transplantation was carrie ...
62 PROjECT PRIDE batching plants, fabrication yards, kiln and mill areas, worker housing, etc. – were arranged for adequate powe ...
COmmENCEmENT OF ExECUTION 63 arose during execution and in overcoming all bottlenecks. A positive and motivational approach with ...
64 PROjECT PRIDE Being a fast-track project, the initial and most important task was to ensure early release of construction dra ...
COmmENCEmENT OF ExECUTION 65 from FLSmidth kept arriving. The construction team worked with great speed and zeal to take up the ...
66 PROjECT PRIDE the execution agencies to mobilize the additional manpower resources to achieve the targeted progress levels. A ...
COmmENCEmENT OF ExECUTION 67 immediately in China and the supplies started arriving at site from March 2019 onwards. All supplie ...
68 PROjECT PRIDE The load centre for LS conveyors was located very close to the existing hopper structure based on techno- econo ...
COmmENCEmENT OF ExECUTION 69 team was pushing the limits of Holtec as well as FLSmidth engineers. There was a meeting organized ...
70 PROjECT PRIDE Project review meeting under the leadership of honourable MD & CEO of Dalmia Cement, Shri Mahendra Singhi J ...
COmmENCEmENT OF ExECUTION 71 commitment and pride in being part of the great success of Project Pride. This motivation level was ...
«