Dalmia DSP Success Story
72 PROjECT PRIDE shut downs of CCBC without affecting production planning of existing plants. It was a challenging task to maint ...
Kiln Erection The project team enthusiastically entered the New Year 2019 with a mammoth task ahead. Work was progressing on all ...
74 PROjECT PRIDE advised us to speed up the work to achieve the target and suggested focusing on the balance work with a proacti ...
KILN ERECTION 75 Kiln shell under manufacturing at FLSmidth Kiln shell in transit passing through barrier Kiln shell received at ...
76 PROjECT PRIDE • Preparation of unloading beds at a designated location • Removal/grounding of power cables fouling in tra ...
KILN ERECTION 77 On 7 March 2019 at 05:00 am, we were informed that the first consignment (two trucks) had reached Liploi Main R ...
78 PROjECT PRIDE The civil team demolished 40 m length of boundary wall in just three hours and the convoy of eight trucks trans ...
KILN ERECTION 79 Making way for eight trucks and unloading Both vehicles were passed below the power supply line well within the ...
80 PROjECT PRIDE 132 kV substation work started in February 2019 As of February 2019 RCC completion was around 40,000 CuM and to ...
KILN ERECTION 81 manufacturing stage and the efforts were to complete the deliveries at the earliest. As of March 2019 major con ...
82 PROjECT PRIDE the balance equipment at the earliest as the erection picked up; the main concern still being that a lot of del ...
KILN ERECTION 83 pictures of the plant to locate space for storage. The operational plant at Rajgangpur supported the project by ...
84 PROjECT PRIDE The season at site getting hotter day by day, but the civil team was determined towards completing the last sla ...
KILN ERECTION 85 With the finalization of layout, considering land constraints, limestone crusher, wagon loading, and railway si ...
86 PROjECT PRIDE a six-week time period instead of the estimated repair time of 8–10 weeks by suppliers. Initially, it was plann ...
KILN ERECTION 87 rope length constraint due to constraint with rope drum. This could lift only 12.5 MT in a 2-fall configuration ...
Plant Commissioning In July 2019, we were struggling to achieve more progress in erection, cable tray fixing and cable laying, d ...
PLANT COmmIssIONINg 89 Site conditions due to heavy rains All site staff including workmen from DCBL, Ayoki, HABPCO, FLSmidth, t ...
90 PROjECT PRIDE happening with their respective team in the respective area with support from HR, admin, safety, and store pers ...
PLANT COmmIssIONINg 91 targets to expedite the punch list and balance finishing works in the respective sections. October 2019 w ...
«